Define YETS duration and date for the 2023 restart.
Action information
Completed ?
From LMC
448
Assignees
EN-ACE BE-OP LMC
Action details
Comments
Organise a new schedule taking into account the experiment and machine constraints.
Action information
Completed ?
From LMC
446
Assignees
EN-ACE BE-OP LPC LSWG
Action details
Comments
Discuss on the grounding necessity, and whether it should be performed on May 9-11.
Action information
Completed ?
From LMC
438
Assignees
TE-CRG BE-ICS SY-RF BE-OP
Action details
Comments
Circulate to the LMC members a machine status by April, 6๐‘กโ„Ž reporting on progress with the machine checkout and the LHC RF recovery, and providing an update to the schedule.
Action information
Completed ?
From LMC
436
Assignees
BE-OP
Action details
Comments
Revisit the safety procedures of the BLM validation campaign in view of autonomous TIM operation.
Action information
Completed ?
From LMC
426
Assignees
BE-CEM BE-OP LHC CSAP HSE-RP
Action details
Comments
Produce a planning for a combined TIM and battery BLM test campaign in view of the Pilot Beam Test and Run3, reporting back to the LMC with the final proposal.
Action information
Completed ?
From LMC
423
Assignees
SY-BI BE-CEM EN-ACE BE-OP
Action details
Comments
Detail the installation plan for the MoEDAL-MAPP experiment in UA83. The go-ahead for any installation will require the approval of the Research Board.
Action information
Completed ?
From LMC
423
Assignees
BE-EA BE-OP
Action details
Comments
To define a new date for the SR4 transformer replacement (after the Pilot Beam Test).
Action information
Completed ?
From LMC
422
Assignees
EN-EL BE-OP EN-ACE SY-RF
Action details
Comments
Update the LS2 and YETS schedules to be consistent with the 6.8 TeV energy target.
Action information
Completed ?
From LMC
419
Assignees
EN-ACE BE-OP
Action details
Comments
Clarify impact of LHC schedule change on the Injector schedule.
Action information
Completed ?
From LMC
416
Assignees
EN-ACE BE-OP
Action details