Actions
Actions list
Assignees Action title Status Open Close ID
BE-OP Investigate if the two weeks planned for the 2026 HWC campaign can be further reduced. LHC Machine Committee (LMC #503) 202
SY-STI Investigate the impact of both H and V crossing plane options on the TCL mitigation strategy for LHCb. Report back to LMC in view of possible TCL procurement by the end of 2025. LHC Machine Committee (LMC #502) 201
ATS groups Remind all personnel about the strict prohibition of crossing safety barriers and fences, and reiterate the necessity of adhering to all safety protocols. LHC Machine Committee (LMC #501) LHC Machine Committee (LMC #502) 200
SY-RF Report back on M1B2 cryomodule performance with beam. LHC Machine Committee (LMC #501) 199
LBOC Following the recommendation of the Edge-Welded Bellows Task Force, ensure that the stroke of all LHC equipment is reduced to the minimum necessary. LHC Machine Committee (LMC #500) 198
TE-MPE Provide BE-OP with a complete picture of the various versions of QPS cards installed for the 2025 run, including their location, and follow agreed procedures for future modifications. LHC Machine Committee (LMC #500) 197
TE-MPE Document the recent QPS system changes in a dedicated ARR. LHC Machine Committee (LMC #499) LHC Machine Committee (LMC #500) 194
LBOC Prepare options and procedures for mitigating a failure of the first D1 module and report back to the LMC in due time. LHC Machine Committee (LMC #499) LHC Machine Committee (LMC #501) 196
BE-OP, TE-MPE, MP3 Validate the recent QPS system changes during the 2025 HWC campaign. LHC Machine Committee (LMC #499) 195
TE-MPE Report back on the recent QPS events in due time. LHC Machine Committee (LMC #498) LHC Machine Committee (LMC #499) 192
ATS groups Check which sectors will be baked out during the EYETS 2024-25 and ensure that there is no impact on their equipment in these regions. LHC Machine Committee (LMC #498) LHC Machine Committee (LMC #499) 193
BE-OP Report back the final 2025 schedule and the updated 2026 draft. LHC Machine Committee (LMC #497) LHC Machine Committee (LMC #499) 189
SY-EPC Report back on the anomalies suspected on the circuit for RQ5.LR3. LHC Machine Committee (LMC #497) LHC Machine Committee (LMC #498) 190
BE-ABP Report back in due time about the flat optics segment of the LHC 2025-26 configuration. LHC Machine Committee (LMC #497) LHC Machine Committee (LMC #499) 191
LPC Report in due time on the potential of an intermediate solution between Scenario B and C, taking into account an 11 weeks YETS and the effect on the cooldown time for the p-Pb run. LHC Machine Committee (LMC #496) LHC Machine Committee (LMC #499) 188
SY-EPC, TE-CRG Report back on the investigation about the correlation between the SVC re-activation and the cryo problem in Point 8. LHC Machine Committee (LMC #494) LHC Machine Committee (LMC #503) 187
ATS groups Provide input on Radiation Resistant Cable requirements to EN-EL by 14 October. LHC Machine Committee (LMC #493) LHC Machine Committee (LMC #494) 186
BE-OP Prepare a plan for an optimal use of the machine time if the repair of the compressor in Point 6 has to be performed sooner than currently scheduled. LHC Machine Committee (LMC #492) LHC Machine Committee (LMC #493) 185
SY-ABT Report back to the LMC on the consolidation proposal for the AC dipole and the possibilities for its upgrade for the HL-era. LHC Machine Committee (LMC #492) 184
EN-EL Clarify the AUG specification procedure and stakeholder involvement for areas involving experiments. LHC Machine Committee (LMC #491) 183
LBOC Track down the root causes of the observed lifetime improvement during the cycle before Stable Beams. LHC Machine Committee (LMC #490) LHC Machine Committee (LMC #501) 182
SY-BI, HSE-RP Investigate the possibility to install additional instrumentation to identify the source of muons for the FASER and SND background. LHC Machine Committee (LMC #487) LHC Machine Committee (LMC #489) 179
EN-MME, TE-VSC Report back on the warm module x-rays performed during TS1. LHC Machine Committee (LMC #487) LHC Machine Committee (LMC #488) 180
EN-EL, TE-VSC Investigate a redundant solution to ensure the availability of the pumping of the insulation vacuum of the Point 5 triplet. LHC Machine Committee (LMC #487) 181
LBOC, BE-ABP, SY-STI Study mitigation strategies to reduce FASER and SND background. LHC Machine Committee (LMC #487) LHC Machine Committee (LMC #501) 178
Task force on the Edge Welded Bellows Report to the Committee the present status of the investigation. LHC Machine Committee (LMC #486) LHC Machine Committee (LMC #500) 177
LBOC, MPP Evaluate if a minimum set of validation checks is required after the polarity changes of LHCb spectrometers. LHC Machine Committee (LMC #486) LHC Machine Committee (LMC #501) 175
BE-OP, SY-BI Commission blindable BLMs in the injection region (Point 2 and /оr 8). LHC Machine Committee (LMC #486) 176
BE-OP Explore the possibility to verify SPS transverse bunch oscillation before extraction to the LHC. LHC Machine Committee (LMC #484) LHC Machine Committee (LMC #485) 174
LBOC, MPP Depending on the 2024 operational experience with the TDIS temperature interlock, define a strategy for the TDIS opening throughout the operational cycle to maximize the bellow lifetime, with input from SY-STI and IWG. LHC Machine Committee (LMC #483) LHC Machine Committee (LMC #484) 173
LS3C Follow-up on the return of experience of the YETS 2023-24 and items remaining from YETS 2022-23. LHC Machine Committee (LMC #482) 172
LBOC Report back on the final choice of the initial collision beta* for the 2024 pp run. LHC Machine Committee (LMC #481) LHC Machine Committee (LMC #483) 170
LMC Chairs, ATS management Decide on the cryogenic configuration for the 2024 ion run. LHC Machine Committee (LMC #481) LHC Machine Committee (LMC #493) 171
ATS Safety Meeting Follow-up on SR buildings access constraints and co-activities during HWC. LHC Machine Committee (LMC #480) 169
SY-ABT, TE-VSC Report back on the final solution for operating the vacuum interlock of the MKIs in 2024. LHC Machine Committee (LMC #479) LHC Machine Committee (LMC #481) 168
TREX, LS3C Propose a strategy for an optimal information flow to coordinate machine and experiment activities during the long shutdowns and end of year stops. LHC Machine Committee (LMC #479) LHC Machine Committee (LMC #483) 167
IWG, BE-ABP Report back on limits for MDs in 2024, after the input from LSWG is received. LHC Machine Committee (LMC #479) LHC Machine Committee (LMC #485) 165
TE-VSC, EN-ACE Add the ZDCs constraints to the bake-out procedures and to scheduling planning. LHC Machine Committee (LMC #479) 166
LMC Define a strategy for increasing bunch intensity in 2024. LHC Machine Committee (LMC #478) LHC Machine Committee (LMC #479) 164
TE dept Put in place a structure to review the RF finger issues involving all the stakeholders. LHC Machine Committee (LMC #477) LHC Machine Committee (LMC #503) 162