LPC Report in due time on the potential of an intermediate solution between Scenario B and C, taking into account an 11 weeks YETS and the effect on the cooldown time for the p-Pb run. LHC Machine Committee (LMC #496) LHC Machine Committee (LMC #499) 188
SY-EPC, TE-CRG Report back on the investigation about the correlation between the SVC re-activation and the cryo problem in Point 8. LHC Machine Committee (LMC #494) LHC Machine Committee (LMC #503) 187
ATS groups Provide input on Radiation Resistant Cable requirements to EN-EL by 14 October. LHC Machine Committee (LMC #493) LHC Machine Committee (LMC #494) 186
BE-OP Prepare a plan for an optimal use of the machine time if the repair of the compressor in Point 6 has to be performed sooner than currently scheduled. LHC Machine Committee (LMC #492) LHC Machine Committee (LMC #493) 185
SY-ABT Report back to the LMC on the consolidation proposal for the AC dipole and the possibilities for its upgrade for the HL-era. LHC Machine Committee (LMC #492) 184
EN-EL Clarify the AUG specification procedure and stakeholder involvement for areas involving experiments. LHC Machine Committee (LMC #491) 183
LBOC Track down the root causes of the observed lifetime improvement during the cycle before Stable Beams. LHC Machine Committee (LMC #490) LHC Machine Committee (LMC #501) 182
EN-EL, TE-VSC Investigate a redundant solution to ensure the availability of the pumping of the insulation vacuum of the Point 5 triplet. LHC Machine Committee (LMC #487) 181
EN-MME, TE-VSC Report back on the warm module x-rays performed during TS1. LHC Machine Committee (LMC #487) LHC Machine Committee (LMC #488) 180
SY-BI, HSE-RP Investigate the possibility to install additional instrumentation to identify the source of muons for the FASER and SND background. LHC Machine Committee (LMC #487) LHC Machine Committee (LMC #489) 179
LBOC, BE-ABP, SY-STI Study mitigation strategies to reduce FASER and SND background. LHC Machine Committee (LMC #487) LHC Machine Committee (LMC #501) 178
Task force on the Edge Welded Bellows Report to the Committee the present status of the investigation. LHC Machine Committee (LMC #486) LHC Machine Committee (LMC #500) 177
BE-OP, SY-BI Commission blindable BLMs in the injection region (Point 2 and /оr 8). LHC Machine Committee (LMC #486) 176
LBOC, MPP Evaluate if a minimum set of validation checks is required after the polarity changes of LHCb spectrometers. LHC Machine Committee (LMC #486) LHC Machine Committee (LMC #501) 175
BE-OP Explore the possibility to verify SPS transverse bunch oscillation before extraction to the LHC. LHC Machine Committee (LMC #484) LHC Machine Committee (LMC #485) 174
LBOC, MPP Depending on the 2024 operational experience with the TDIS temperature interlock, define a strategy for the TDIS opening throughout the operational cycle to maximize the bellow lifetime, with input from SY-STI and IWG. LHC Machine Committee (LMC #483) LHC Machine Committee (LMC #484) 173
LS3C Follow-up on the return of experience of the YETS 2023-24 and items remaining from YETS 2022-23. LHC Machine Committee (LMC #482) 172
LMC Chairs, ATS management Decide on the cryogenic configuration for the 2024 ion run. LHC Machine Committee (LMC #481) LHC Machine Committee (LMC #493) 171
LBOC Report back on the final choice of the initial collision beta* for the 2024 pp run. LHC Machine Committee (LMC #481) LHC Machine Committee (LMC #483) 170
ATS Safety Meeting Follow-up on SR buildings access constraints and co-activities during HWC. LHC Machine Committee (LMC #480) 169
SY-ABT, TE-VSC Report back on the final solution for operating the vacuum interlock of the MKIs in 2024. LHC Machine Committee (LMC #479) LHC Machine Committee (LMC #481) 168
TREX, LS3C Propose a strategy for an optimal information flow to coordinate machine and experiment activities during the long shutdowns and end of year stops. LHC Machine Committee (LMC #479) LHC Machine Committee (LMC #483) 167
TE-VSC, EN-ACE Add the ZDCs constraints to the bake-out procedures and to scheduling planning. LHC Machine Committee (LMC #479) 166
IWG, BE-ABP Report back on limits for MDs in 2024, after the input from LSWG is received. LHC Machine Committee (LMC #479) LHC Machine Committee (LMC #485) 165
LMC Define a strategy for increasing bunch intensity in 2024. LHC Machine Committee (LMC #478) LHC Machine Committee (LMC #479) 164
LMC Define a global strategy for increasing the beam and bunch intensity in 2024 and investigate the possibility of running with degraded vacuum conditions due to an RF finger issue. LHC Machine Committee (LMC #477) LHC Machine Committee (LMC #479) 163
TE dept Put in place a structure to review the RF finger issues involving all the stakeholders. LHC Machine Committee (LMC #477) LHC Machine Committee (LMC #503) 162
LMC Chairs Consider a global coordination of information and issues related to bellows in the LHC machine. LHC Machine Committee (LMC #477) LHC Machine Committee (LMC #480) 161
TE-VSC, LHCb VeLo team Document and provide training to the relevant teams about the sequence of actions to be taken for the different failure scenarios of the VeLo vacuum system. LHC Machine Committee (LMC #476) LHC Machine Committee (LMC #511) 160
EN-EL Follow-up on the planning and impact of the power cut during the AUG tests on machine equipment. LHC Machine Committee (LMC #476) LHC Machine Committee (LMC #477) 158
BE-OP GL, Energy coordinator Report on the cost and constraint to schedule the LHC YETS 2024-25 start two weeks before End-Of-Year Closure. LHC Machine Committee (LMC #476) LHC Machine Committee (LMC #481) 159
RF Burst Disc Task Force, LHC CSAP Review the access conditions around the fast-depressurizing valves on the ACS cryomodules. LHC Machine Committee (LMC #475) LHC Machine Committee (LMC #478) 157
LBOC Follow up and report back on the understanding of losses during injection. LHC Machine Committee (LMC #466) 153
MPP Comment on the possibility to test and operationally deploy blindable BLMs, in the injection region and in Point 7. LHC Machine Committee (LMC #466) LHC Machine Committee (LMC #486) 154
TE-VSC, EN-ACE, BE-OP Schedule an X-rays analysis of the IR5 RF finger warm modules at the earliest opportunity. LHC Machine Committee (LMC #466) LHC Machine Committee (LMC #474) 156
TDIS Task Force Report back the TDIS beam screen heating effects findings after summer 2023. LHC Machine Committee (LMC #466) LHC Machine Committee (LMC #486) 155
LHC CSAP, BE-OP-TI Clarify access rules when the tunnel ventilation is in a degraded mode of operation. LHC Machine Committee (LMC #465) 151
SY-EPC, EN-EL, BE-OP-TI Clarify and communicate the procedure for turning on the SVCs after a trip. LHC Machine Committee (LMC #465) LHC Machine Committee (LMC #487) 149
SY-STI Report on the understanding of the observations of the TDIS temperature issue and come back with a strategy to alleviate the TDIS interlock limitation. LHC Machine Committee (LMC #465) LHC Machine Committee (LMC #466) 150
LPC, MPP Report back the final VeLo minimum gap strategy. LHC Machine Committee (LMC #465) LHC Machine Committee (LMC #466) 152