Follow-up on the planning and impact of the power cut during the AUG tests on machine equipment. Action information #158 Action Completed ? From LMC 476 Assignees EN-EL Action details Comments
Clarify and communicate the procedure for turning on the SVCs after a trip. Action information #149 Action Completed ? From LMC 465 Assignees SY-EPC EN-EL BE-OP-TI Action details Comments
Report back after the mid-2022 visual inspection for an update on the status of the LHC UPS batteries. Action information #61 Action Completed ? From LMC 430 Assignees EN-EL Action details Comments
Follow-up on the recent UPS incidents. Action information #56 Action Completed ? From LMC 429 Assignees EN-EL Action details Comments
To define a new date for the SR4 transformer replacement (after the Pilot Beam Test). Action information #38 Action Completed ? From LMC 422 Assignees EN-EL BE-OP EN-ACE SY-RF Action details Comments