Report back on the final solution for operating the vacuum interlock of the MKIs in 2024.
Action information
Completed ?
From LMC
479
Assignees
SY-ABT TE-VSC
Action details
Comments
Add the ZDCs constraints to the bake-out procedures and to scheduling planning.
Action information
Completed ?
From LMC
479
Assignees
TE-VSC EN-ACE
Action details
Comments
Document and provide training to the relevant teams about the sequence of actions to be taken for the different failure scenarios of the VeLo vacuum system.
Action information
Completed ?
From LMC
476
Assignees
TE-VSC LHCb VeLo team
Action details
Comments
Schedule an X-rays analysis of the IR5 RF finger warm modules at the earliest opportunity.
Action information
Completed ?
From LMC
466
Assignees
TE-VSC EN-ACE BE-OP
Action details
Comments
TE-VSC module task force to report back to LMC, including any possible intensity limitations, in due time.
Action information
Completed ?
From LMC
464
Assignees
TE-VSC
Action details
Comments
Report in due time on the Phase II vacuum recovery of the LHCb VeLo.
Action information
Completed ?
From LMC
456
Assignees
LHCb collaboration TE-VSC
Action details
Comments
Report on observed vacuum activities in IR4 (5R4.B2) and its correlation with measured dose.
Action information
Completed ?
From LMC
453
Assignees
TE-VSC R2E LBOC
Action details

Added LBOC a posteriori as they follow up for the LMC.

Comments
Report back on the vacuum issues in 5R4.
Action information
Completed ?
From LMC
452
Assignees
TE-VSC
Action details

Better explained in action 118 (closed ex officio).

Comments
Investigate any anomalous loss patterns from the Pilot Beam Test to possibly identify similar issues elsewhere than 21L3.
Action information
Completed ?
From LMC
428
Assignees
TE-VSC BE-ABP
Action details
Comments
Follow up with TREX for the preparation of procedures for possible interventions on the the VELO Wake Field Suppressor.
Action information
Completed ?
From LMC
422
Assignees
LHCb collaboration TREX TE-VSC
Action details
Comments