Clarify and communicate the procedure for turning on the SVCs after a trip.
Action information
Completed ?
From LMC
465
Assignees
SY-EPC EN-EL BE-OP-TI
Action details
Comments
Implement the proposed changes to the procedures to avoid non-conformities similar to that of RTQX2.L5 reoccurring.
Action information
Completed ?
From LMC
461
Assignees
SY-EPC
Action details

Email by M. Cerqueira Bastos on 2023.06.07 (closed together with twin action on LMC 467)

Comments
Report on the outcome of the investigation on the non-conformity in the Point 5 RTQX2 circuit.
Action information
Completed ?
From LMC
458
Assignees
SY-EPC
Action details
Comments
Carry out a return of experience analysis on the renaming procedure after a power converter exchange, and report back on the outcome.
Action information
Completed ?
From LMC
444
Assignees
SY-RF SY-EPC
Action details

from Andy Butterworth:

"The procedure for the renaming of the power converter in the RF control system is now documented in the EPC procedure as well as in the RF wiki.
After an exchange of power converter the HL RF piquet will contact an RF controls expert to make the change. No other controls modifications (LSA etc.) are necessary."

Comments
Define the applicability of ARRs to power converter exchanges.
Action information
Completed ?
From LMC
427
Assignees
SY-EPC EN-ACE
Action details

Archive at the end of year (last meeting of the year).

Comments