LPC

LPC

Report back the final VeLo minimum gap strategy.
Action information
Completed ?
From LMC
465
Assignees
LPC MPP
Action details
Comments
Report back on the results of the VeLo tomography (400 bunches and 6.8 TeV fill)
Action information
Completed ?
From LMC
460
Assignees
LPC MPP
Action details
Comments
Quantify the effect of the crossing angle polarity change in IR1 on the FASER detector acceptance and on its overall performance.
Action information
Completed ?
From LMC
459
Assignees
LPC
Action details
Comments
Investigate the recent dumps due to the ATLAS BCM (fast losses for high intensity beam).
Action information
Completed ?
From LMC
453
Assignees
LPC
Action details
Comments
Confirm with the LHCb team if the option of reduced scan range is viable, and report on the final result of the tolerances analysis and chosen option for the vdM optics.
Action information
Completed ?
From LMC
451
Assignees
LPC LHCb collaboration
Action details
Comments
Experiments to provide feedback on any impact of using the hybrid beam schemes.
Action information
Completed ?
From LMC
448
Assignees
LPC
Action details

Answered during Chamonix 2023 workshop.

Comments
Present the outcome of the discussions on the 2022 schedule and Run 3 program.
Action information
Completed ?
From LMC
448
Assignees
LPC LMC
Action details
Comments
Define the agreed schedule for the remaining machine time in 2022.
Action information
Completed ?
From LMC
447
Assignees
LPC LMC
Action details
Comments
Organise a new schedule taking into account the experiment and machine constraints.
Action information
Completed ?
From LMC
446
Assignees
EN-ACE BE-OP LPC LSWG
Action details
Comments