Evaluate if a minimum set of validation checks is required after the polarity changes of LHCb spectrometers. Action information #175 Action Completed ? From LMC 486 Assignees LBOC MPP Action details Comments
Depending on the 2024 operational experience with the TDIS temperature interlock, define a strategy for the TDIS opening throughout the operational cycle to maximize the bellow lifetime, with input from SY-STI and IWG. Action information #173 Action Completed ? From LMC 483 Assignees LBOC MPP Action details Comments
Comment on the possibility to test and operationally deploy blindable BLMs, in the injection region and in Point 7. Action information #154 Action Completed ? From LMC 466 Assignees MPP Action details Comments
Report back the final VeLo minimum gap strategy. Action information #152 Action Completed ? From LMC 465 Assignees LPC MPP Action details Comments
Confirm the procedure for the ramp up and minimum gap for the LHCb VeLo closing. Action information #144 Action Completed ? From LMC 463 Assignees MPP Action details Comments
Report back on the results of the VeLo tomography (400 bunches and 6.8 TeV fill) Action information #139 Action Completed ? From LMC 460 Assignees LPC MPP Action details Comments
Confirm the possibility to use the Beam 2 BBLR wires in operation, and determine the additional commissioning time required. Action information #130 Action Completed ? From LMC 460 Assignees MPP LBOC Action details Comments
Decide on the final option for TCLIA operation. Action information #86 Action Completed ? From LMC 442 Assignees SY-ABT MPP Action details Comments
Report back on the analysis for the LHCb request to set the VeLo at 15 mm. Action information #82 Action Completed ? From LMC 439 Assignees MPP Action details Comments
Followup of the MP implications of luminosity levelling, and report back on the results to the LMC. Action information #72 Action Completed ? From LMC 434 Assignees MPP Action details Comments