Report back on the analysis for the LHCb request to set the VeLo at 15 mm.
Action information
Completed ?
From LMC
439
Assignees
MPP
Action details
Comments
Followup of the MP implications of luminosity levelling, and report back on the results to the LMC.
Action information
Completed ?
From LMC
434
Assignees
MPP
Action details
Comments
Follow-up of the luminosity levelling strategy in 2022 and its staging by taking into account operational and Machine Protection constraints.
Action information
Completed ?
From LMC
419
Assignees
MPP LBOC
Action details

Presentation by C. Wiesner in Evian:

https://indico.cern.ch/event/1077835/contributions/4533377/attachments/2352931/4014870/Wiesner_Evian21_MPS_view_on_commissioning.pdf

Comments