Follow-up on the cause of the Point 5 evacuation alarm on November 30th 2021. Action information #55 Action Completed ? From LMC 429 Assignees EN-ACE Action details Comments
Circulate the ARR documents for comments and eventual approval. Action information #53 Action Completed ? From LMC 427 Assignees EN-ACE Action details Comments
Define the applicability of ARRs to power converter exchanges. Action information #52 Action Completed ? From LMC 427 Assignees SY-EPC EN-ACE Action details Archive at the end of year (last meeting of the year). Comments
Produce a planning for a combined TIM and battery BLM test campaign in view of the Pilot Beam Test and Run3, reporting back to the LMC with the final proposal. Action information #42 Action Completed ? From LMC 423 Assignees SY-BI BE-CEM EN-ACE BE-OP Action details Comments
Circulate ECR (EDMS 2617044) for approval by the LMC. Action information #40 Action Completed ? From LMC 423 Assignees BE-EA EN-ACE Action details Comments
To define a new date for the SR4 transformer replacement (after the Pilot Beam Test). Action information #38 Action Completed ? From LMC 422 Assignees EN-EL BE-OP EN-ACE SY-RF Action details Comments
Update the LS2 and YETS schedules to be consistent with the 6.8 TeV energy target. Action information #27 Action Completed ? From LMC 419 Assignees EN-ACE BE-OP Action details Comments
Clarify impact of LHC schedule change on the Injector schedule. Action information #17 Action Completed ? From LMC 416 Assignees EN-ACE BE-OP Action details Comments
Report back on the advancement of the MB.B28L8 replacement. Action information #16 Action Completed ? From LMC 416 Assignees EN-ACE TE-MSC Action details Comments
Follow-up of the 11L4 misalignment in Sector 34 and its potential impact on the machine aperture. Action information #12 Action Completed ? From LMC 409 Assignees BE-ABP BE-GM EN-ACE TE-MSC Action details Comments