Assignees Action title Status Open Close ID
EN-ACE Follow-up on the YETS25-26 open points from the return of experience. LHC Machine Committee (LMC #526) 236
R2E, MCWG Study the radiation levels at the PICv2 installation in UA83-87 and identify whether mitigation measures are required. LHC Machine Committee (LMC #526) 237
TF for mitigation of collimator end-of-life in the HL era Produce a final document to include: comprehensive overview of available and missing spares for critical collimators, including procurement lead times, overview of components that can be recovered [...] and a comparison of alternatives scenarios [...] LHC Machine Committee (LMC #526) 233
TF for mitigation of collimator end-of-life in the HL era Produce a summary table combining all the relevant data shown in the presentation. LHC Machine Committee (LMC #526) 232
SY-STI, BE-CEM Study possible alternative solutions for collimator LVDT calibrations and mechanical maintenance that do not include fully opening the collimators. LHC Machine Committee (LMC #526) 234
BE-ABP, SY-STI Study the impact of losing more than one non-critical collimator on machine performance. LHC Machine Committee (LMC #526) 235
LSWG Prepare a full schedule for the high intensity test period, including MDs, for approval at the LMC. LHC Machine Committee (LMC #522) 231
MPP Analyse the results of the blindable BLM test and propose a strategy for deployment if deemed necessary. LHC Machine Committee (LMC #522) 229
LBOC Understand the alignment issues related to the TCDQ and TDIS. LHC Machine Committee (LMC #522) 230
SO-SCE Prepare an LS3 inspection/intervention plan to minimize water infiltrations risks in the LHC tunnel. In the shorter term, once conditions allow, re-establish the full operability of the Sector 34 mono-rail in time for the TIM RP survey at the end of Run3. LHC Machine Committee (LMC #521) LHC Machine Committee (LMC #528) 225
SM18 coordination Investigate how RF cryomodule M1B2 testing and refurbishment during LS3 can be integrated into SM18 activities. LHC Machine Committee (LMC #521) LHC Machine Committee (LMC #528) 227
TE-MSC Investigate the feasibility of the RQT12.R8B2 exchange or repair during LS3. LHC Machine Committee (LMC #521) LHC Machine Committee (LMC #522) 226
ATSMB Decide on how to coordinate and resource R2E related activities that need to take place in Point 8 during LS3 regardless of the LHCb upgrade. LHC Machine Committee (LMC #521) LHC Machine Committee (LMC #528) 228
EN-ACE Report, in due time, the return of experience on the short YETS2025-26. LHC Machine Committee (LMC #520) LHC Machine Committee (LMC #526) 224
BGSWG Follow up on the ALICE and LHCb backgrounds with ions, and report back in due time. LHC Machine Committee (LMC #520) 223
BGSWG Follow up on the ALICE background degradation with - /- polarity, and report back in due time. LHC Machine Committee (LMC #519) LHC Machine Committee (LMC #520) 222
SY-STI, BE-OP, BE-ABP Limit the collimator movement to a minimum wherever possible. LHC Machine Committee (LMC #514) LHC Machine Committee (LMC #526) 220
LSWG Compile a prioritized list of MDs that must take place before the end of Run for both protons and ions. LHC Machine Committee (LMC #514) LHC Machine Committee (LMC #525) 221
TE-MPE, MPP, BE-OP Investigate the possibility to include some of the RQS circuits in the PIC during the next YETS, after having checked the relevant failure cases. LHC Machine Committee (LMC #513) LHC Machine Committee (LMC #526) 217
BE-OP, BE-ABP Investigate the possibility of installing a solenoid in 6L2 to limit the ecloud effect if required for the MD program. LHC Machine Committee (LMC #513) LHC Machine Committee (LMC #521) 218
ATS groups Take note of the deadlines for approval of the ECRs (February 2026) and for integration (December 2025) for LS3 activities. LHC Machine Committee (LMC #513) LHC Machine Committee (LMC #514) 219
BE-OP Rework the 2026 draft schedule taking into account LMC input. LHC Machine Committee (LMC #512) LHC Machine Committee (LMC #518) 216
SY-RF, BE-OP Investigate strategies to consolidate the ADT setting management to avoid issues when transitioning to different operational modes. LHC Machine Committee (LMC #511) 214
EN-HE, TIOC Understand the reason for the missed PX15 elevator alarm and put in place a fix to ensure that this does not reoccur. LHC Machine Committee (LMC #511) LHC Machine Committee (LMC #528) 215
SY-STI Report back on the general spares strategy for all collimators in the HL era. LHC Machine Committee (LMC #510) LHC Machine Committee (LMC #526) 213
SY-ABT, BE-OP Investigate possible stroke reductions or fixed garage position also for the TCLIB in Point 2. LHC Machine Committee (LMC #510) LHC Machine Committee (LMC #513) 212
SY-STI Report back on the strategy for mitigating the issue with the TCLIB.6L8 and any eventual intervention in the next YETS. LHC Machine Committee (LMC #510) LHC Machine Committee (LMC #513) 211
SY-STI Prepare the TCLIB spare in readiness for an eventual exchange. LHC Machine Committee (LMC #509) LHC Machine Committee (LMC #513) 207
ATS groups Take note of the list of upcoming roadworks during the 2025-2029 period, and provide feedback if needed. LHC Machine Committee (LMC #509) LHC Machine Committee (LMC #510) 210
ATS groups Verify the new version of the LS3 master schedule, and give feedback to EN-ACE-OSS if needed. LHC Machine Committee (LMC #509) LHC Machine Committee (LMC #510) 209
MPP, SY-STI, SY-ABT Given the present status of the TCLIB.A6L8 (jaws blocked in garage position), report back on the risk analysis and recommendations for the high intensity run. LHC Machine Committee (LMC #509) LHC Machine Committee (LMC #510) 208
BE-ABP Investigate and report back on the increased background observed by SND and FASER. LHC Machine Committee (LMC #508) LHC Machine Committee (LMC #528) 206
EN-ACE Circulate the EYETS post-mortem action list to the scientific secretaries of LMC, LS3C and IEFC to dispatch the EYETS post-mortem actions, accordingly to their subject, to the different Committees. LHC Machine Committee (LMC #507) LHC Machine Committee (LMC #510) 205
BE-ICS Report back on the PLC failure rates after the upgrades of the TE-CRG systems are completed. LHC Machine Committee (LMC #506) 204
BE-OP Consistent with the LMC 484 decision, implement a TDIS parking position of 40 mm instead of its nominal parking position of 55 mm during p-p operation. For Pb-Pb operation and p-p VdM runs, the TDIS parking position will need to be reverted to its nominal LHC Machine Committee (LMC #504) LHC Machine Committee (LMC #505) 203
BE-OP Investigate if the two weeks planned for the 2026 HWC campaign can be further reduced. LHC Machine Committee (LMC #503) 202
SY-STI Investigate the impact of both H and V crossing plane options on the TCL mitigation strategy for LHCb. Report back to LMC in view of possible TCL procurement by the end of 2025. LHC Machine Committee (LMC #502) LHC Machine Committee (LMC #528) 201
SY-RF Report back on M1B2 cryomodule performance with beam. LHC Machine Committee (LMC #501) LHC Machine Committee (LMC #521) 199
ATS groups Remind all personnel about the strict prohibition of crossing safety barriers and fences, and reiterate the necessity of adhering to all safety protocols. LHC Machine Committee (LMC #501) LHC Machine Committee (LMC #502) 200
LBOC Following the recommendation of the Edge-Welded Bellows Task Force, ensure that the stroke of all LHC equipment is reduced to the minimum necessary. LHC Machine Committee (LMC #500) LHC Machine Committee (LMC #526) 198