Review the access conditions around the fast-depressurizing valves on the ACS cryomodules. Action information #157 Action Completed ? From LMC 475 Assignees RF Burst Disc Task Force LHC CSAP Action details Comments
Investigate the preventive exchange of 2 burst discs during TS1. Action information #145 Action Completed ? From LMC 463 Assignees SY-RF EN-ACE RF Burst Disc Task Force Action details Comments
Report back on the feasibility of installing a new control valve with full section opening to act in a similar way to the Warm Recovery Line. Action information #146 Action Completed ? From LMC 463 Assignees RF Burst Disc Task Force Action details Comments
Formalize the procedures for a prompt intervention of the specialists in the different He venting scenarios of the RF cavities. Action information #137 Action Completed ? From LMC 460 Assignees RF Burst Disc Task Force Action details https://edms.cern.ch/document/2905906/ Comments
Report back on the advancement on the investigations of the Point 4 event on April 1st, 2023 and the progress in the understanding the observed time delay between the release valves trigger and the premature rupture of the discs. Action information #136 Action Completed ? From LMC 460 Assignees RF Burst Disc Task Force Action details Comments
Investigate short and long term mitigations for such events in case of loss of cryogenic conditions in the RF cryo-modules. Action information #94 Action Completed ? From LMC 446 Assignees RF Burst Disc Task Force Action details Comments
Report back on the requirements, conditions, and procedure for warm-up of the RF cryomodules. Action information #97 Action Completed ? From LMC 447 Assignees RF Burst Disc Task Force Action details Comments
Report back on additional findings and final plans at the end of the work of the RF Task Force. Action information #91 Action Completed ? From LMC 445 Assignees RF Burst Disc Task Force Action details Comments